Model Building Schedule - 2010 Series

 

Model Building Schedule - PDF Copy
Updated version approved by the MRO Model Building Subcommittee on 12/4/09.
PLEASE NOTE:

** Tasks shown in blue font are to be completed by the Data Representatives. **

**Tasks shown in red font are to be completed by MISO Staff.**
Task Due Date
MOD Base Case Review Finished December 1, 2009
Data Request Sent Out by Email December 11, 2009
Data Request Confirmation Due (See Note 1) December 18, 2009
Company Workbooks Due January 15, 2010
MRO Staff Post Company Workbook Reviews January 22, 2010
Finalize Company Workbooks February 5, 2010
Power Flow (Pass1) data, Dynamics Model data and EIA 411 Confirmation Due (See Note 2) February 19, 2010
Inter-regional Ties Due February 19, 2010
MOD Pass1 Case Create Initiated February 22, 2010
Wind Data Due (not a NERC compliance obligation) March 5, 2010
Machine Reactive Capability Data Due
(not a NERC compliance obligation)
March 5, 2010
Post (Pass1) Solved Power Flow Models March 5, 2010
(With MBS Selected MMWG Externals)
March 5, 2010
Post Dynamics Data for Review March 5, 2010
Dynamics Review Complete Confirmation Due March 19, 2010
Initial start/run of Dynamics Data (errors flagged by DYRE) March 19, 2010
MRO Staff Post Dynamics Review Results April 2, 2010
Corrections to Dynamics Data Due April 16, 2010

Changes to Pass 1 Models and Confirmation Due
(See Note 3)

April 16, 2010
MOD Pass2 Case Create Initiated
(With MBS Selected MMWG Externals)
April 19, 2010

Post (Pass 2) Solved Power Flow Models
(With MBS Selected MMWG External)

April 30, 2010
Post ACCC Results May 7, 2010
Changes to Pass 2 Models and Confirmation Due
(IDEV updates and the same update to MOD)
May 14, 2010
Post (Pass 3) Solved Power Flow Models May 21, 2010
Dynamics Data Checked Against Pass 3 Models May 21, 2010
Changes to Pass 3 Models and Confirmation Due May 28, 2010

Begin Benchmarking of Power flow and Dynamic Models
(See Note 4)

May 28, 2010
MBS Power flow and Dynamic Documentation Due May 28, 2010
Final Series Power flow Models Posted June 18, 2010
Steady State Runs Completed and Dynamics Package Posted June 18, 2010
Post Power flow and Dynamic Documentation June 18, 2010
MRO Submits Model Data to ERAG MMWG
(Deadline for MRO to meet NERC Compliance)
July 13, 2010
Notes
1. The Data Representative must confirm receipt of the data request and review of the project schedule. 
2. The power flow and dynamic data is due by February 19.  The EIA 411 confirmation is simply a statement that your company’s load forecast, which is represented in the models, is consistent with the EIA 411 data submission.  The model loads can differ from the EIA 411 data for any valid reason such as your company adopting a revised forecast since the latest EIA 411 data submission.  
3. Each Data Representative must review all models and fix any modeling errors by April 9.  The review of Pass 1 models should fix all known errors, and the subsequent review of the Pass 2 models should confirm that the models are correct or require minor corrections.  Significant corrections to the Pass 2 models will necessitate the Data Representative receiving MBS approval prior to the change being implemented, since such changes will force the posting of Pass 3 models for a general review.
4. The model building contractor staff will perform benchmarking of the models. The benchmarking results will be part of the model documentation.