| Model Building Schedule - 2010 Series |
|
 |
Model Building Schedule - PDF Copy |
| Approved by the MRO Model Building Subcommittee on: 06/03/10. |
| PLEASE NOTE: |
** Tasks shown in blue font are to be completed by the Data Representatives. ** |
| **Tasks shown in red font are to be completed by MISO Staff.** |
|
| Task |
Due Date |
| MOD Base Case Review Finished |
December 1, 2009 |
| Data Request Sent Out by Email |
December 11, 2009 |
| Data Request Confirmation Due (See Note 1) |
December 18, 2009 |
| Company Workbooks Due |
January 15, 2010 |
| MRO Staff Post Company Workbook Reviews |
January 22, 2010 |
| Finalize Company Workbooks |
February 5, 2010 |
| Power Flow (Pass1) data, Dynamics Model data and EIA 411 Confirmation Due (See Note 2) |
February 19, 2010 |
| Inter-regional Ties Due |
February 19, 2010 |
| MOD Pass1 Case Create Initiated |
February 22, 2010 |
| Wind Data Due (not a NERC compliance obligation) |
March 5, 2010 |
Machine Reactive Capability Data Due (not a NERC compliance obligation) |
March 5, 2010 |
Post (Pass1) Solved Power Flow Models March 5, 2010
(With MBS Selected MMWG Externals) |
March 5, 2010 |
| Post Dynamics Data for Review |
March 5, 2010 |
| Dynamics Review Complete Confirmation Due |
March 19, 2010 |
| Initial start/run of Dynamics Data (errors flagged by DYRE) |
March 19, 2010 |
| MRO Staff Post Dynamics Review Results |
April 2, 2010 |
| Corrections to Dynamics Data Due |
April 16, 2010 |
Changes to Pass 1 Models and Confirmation Due
(See Note 3) |
April 16, 2010 |
MOD Pass2 Case Create Initiated
(With MBS Selected MMWG Externals) |
April 19, 2010 |
Post (Pass 2) Solved Power Flow Models (With MBS Selected MMWG External) |
May 10, 2010 |
| Post ACCC Results |
May 14, 2010 |
Changes to Pass 2 Models and Confirmation Due
(IDEV updates and the same update to MOD) |
May 21, 2010 |
| Post (Pass 3) Solved Power Flow Models |
May 28, 2010 |
| Dynamics Data Checked Against Pass 3 Models |
May 28, 2010 |
| MBS Power flow and Dynamic Documentation Due |
May 28, 2010 |
| Changes to Pass 3 Models and Confirmation Due |
June 11, 2010 |
Begin Benchmarking of Power flow and Dynamic Models
(See Note 4) |
July 7, 2010* |
| Post (Pass 4) Solved Power Flow Models |
July 7, 2010* |
| Final Series Power flow Models and Documentation Posted |
July 7, 2010* |
| Dynamics Package and Documentation Posted |
July 28, 2010* |
MRO Submits Model Data to ERAG MMWG
(Deadline for MRO to meet NERC Compliance) |
July 7, 2010* |
| * Updated 7/7/2010 by MRO staff to reflect actual or expected posting dates |
|
| Notes |
| 1. |
The Data Representative must confirm receipt of the data request and review of the project schedule. |
| 2. |
The power flow and dynamic data is due by February 19. The EIA 411 confirmation is simply a statement that your company’s load forecast, which is represented in the models, is consistent with the EIA 411 data submission. The model loads can differ from the EIA 411 data for any valid reason such as your company adopting a revised forecast since the latest EIA 411 data submission. |
| 3. |
Each Data Representative must review all models and fix any modeling errors by April 9. The review of Pass 1 models should fix all known errors, and the subsequent review of the Pass 2 models should confirm that the models are correct or require minor corrections. Significant corrections to the Pass 2 models will necessitate the Data Representative receiving MBS approval prior to the change being implemented, since such changes will force the posting of Pass 3 models for a general review. |
| 4. |
The model building contractor staff will perform benchmarking of the power flow models, and MRO staff will perform benchmarking of the Dynamics models. The benchmarking results will be part of the model documentation. |
|
|
|